Ho Chi Minh City continues canal project
(10:53:09 AM 11/10/2014)The project comprises three implementation stages, including the construction of a 38ha wastewater treatment plant for the Nhieu Loc-Thi Nghe Canal.
The plant, located in District 2's Thanh My Loi ward, has a capacity of 480,000m3 per day. Construction on the plant includes an 8km drainage system with pipes 320cm in diameter.
According to the municipal People’s Committee, the facility, which is expected to be completed in 2020, will collect wastewater from the entire basin and treat it before discharging the clean water into the Saigon River and Dong Nai River.
The first phase of the project commenced in 2003 and was completed in August 2012, at a total cost of 8.6 trillion VND (421 million USD), with 6.126 trillion VND (294 million USD) coming from World Bank ODA.
The Ho Chi Minh City environmental sanitation (Nhieu Loc-Thi Nghe Basin) project is one of the city's large-scale environmental projects.
The Nhieu Loc-Thi Nghe Canal comprises 33km2 and runs through districts 1, 3, 10, Phu Nhuan, Tan Binh, Go Vap and Binh Thanh.
The canal has an important role in managing and preventing flooding, which is a common occurance in the municipality during the rainy season, benefitting as many as 1.5 million residents.
You may also be interested in:
-
German Government continues to support MRC for sustainable development of the Lower Mekong Basin
-
Water in Gia Dinh canal black from pollution, rubbish
-
Phu Yen water-supply plants break down as water shortage worsens
-
HCM City to spend trillions of dong on wastewater treatment plants
-
Leprosy villagers lead miserable lives because of dirty water
-
What will happen if there is no more sand in the Mekong River Delta?
-
Nation's water security threat has reached alarming proportions
-
Grievous misuse of environmental protection fees
-
“Cancer village” in Hanoi still doesn’t have clean water
Recent Posts:
- USAID Launches New Public Service Announcements to Tackle Rhino Horn Consumption (19/12/2019)
- Youth for Climate Cycling Event (within the framework of European Climate Diplomacy Week 2019) (28/09/2019)
- VIETNAM: New Study Offers Pathways To Climate-Smart Transport (17/09/2019)
- USAID works alongside Viet Nam’s National Assembly on effective wildlife conservation through demand reduction (26/07/2019)
- Winners of TRAFFIC’s sustainable traditional medicine competition announced (22/06/2019)
- Hanoi mobilizes resources to improve the city’s air quality (28/11/2018)
- Accelerating the implementation of the Paris Agreement in Viet Nam through joint national and international efforts (07/11/2018)
- USAID Promotes Chi Initiative to Drive Down Demand for Rhino Horn (28/08/2018)
- Siemens supplies equipment for Vietnam’s largest solar farm (14/07/2018)
- Members of Vietnamese and German companies take pledge against wildlife crime (30/06/2018)

Ash treatment required before thermal-power plant construction
(Tinmoitruong.vn) - The government has told investors not to build coal thermal power plants if they don’t have solutions to treat ash, thus causing pollution.

Decree requires waste importers to place deposits on scrap
(Tinmoitruong.vn) - Importers have to make a deposit for scrap materials imported from June 15, 2015 as per government decree No 38. This will place a heavy financial burden on enterprises.

HCM City to hike water tariffs by 50% over five years
(Tinmoitruong.vn) - Plans to increase water tariffs in HCM City by 10.5 per cent annually in 2015-19 are part of a water supply master plan submitted recently to the city People's Committee for approval by related departments.